Public Reel

The story of Hoover Dam

US Government work A work of the United States Government, which US copyright does not cover (17 U.S.C. 105). Record.

Frame from the Internet Archive copy gov.archives.arc.37058
Copy
gov.archives.arc.37058 on the Internet Archive
Read
231 shots over 27:37 · 409 transcript lines · JSON
Record
The story of Hoover Dam US Government work
Wrong?
Report a problem
Lands on the shot covering that second.

Similar frames

By the average clip vector of the keyframes; a measurement, not a judgement

How this page was made

231 shots over 27:37, read from the Internet Archive copy gov.archives.arc.37058 (gov.archives.arc.37058_512kb.mp4, 320×240, 29.97 fps). Shot boundaries by PySceneDetect's adaptive detector; each frame links to the Archive's player at that second. Government-works dossier: The story of Hoover Dam US Government work. JSON

Measurements: colour film on its keyframes (231 of 231 shots judged colour), average shot 7.2s long, a frontal face detected in 3% of keyframes. Shots are detected automatically and each is represented by its midpoint frame.

Transcript

Machine transcription of the Archive copy's audio with Whisper large-v3-turbo (temperature 0); the model heard it as en. 409 segments kept, 40 dropped as the kind of hallucination the model produces over music and silence. Each timestamp links to the Archive's player at that second. This has not been checked against the film and can be wrong.

  1. 0:08 This is the story of Hoover Dam.
  2. 0:11 one of America's seven modern civil engineering wonders.
  3. 0:37 Build a dam in the wilderness and the world will beat a path to it.
  4. 0:42 For many centuries,
  5. 0:43 This was a lonely canyon, unseen and untouched by man.
  6. 0:47 scorched by a desert sun.
  7. 0:50 Scolded by an angry river slashing its way to the Mother Sea,
  8. 0:55 Now it lies peaceful and silent.
  9. 0:58 except for the gentle hum of a hydroelectric power plant.
  10. 1:01 The bubbling up of water as it leaves mighty turbines
  11. 1:05 the cheerful sounds of America and the world on the move.
  12. 1:09 to see this pioneer multipurpose reclamation project
  13. 1:13 Man built in Black Canyon.
  14. 1:17 Millions come to this once desolate spot
  15. 1:20 to see this engineering wonder.
  16. 1:23 to hear the story of Hoover Dam.
  17. 1:26 Ladies and gentlemen...
  18. 1:27 We're now standing on the powerhouse ramp
  19. 1:30 560 feet below the top of the dam.
  20. 1:34 This is Black Canyon.
389 more segments
  1. 1:35 where Nevada and Arizona meet.
  2. 1:38 where the Colorado River once flowed uncontrolled.
  3. 1:41 Here is where man conquered this mighty river.
  4. 1:44 placing a concrete yoke about his neck.
  5. 1:46 to harness its tremendous water and power resources.
  6. 1:50 The water that flows through the canyon...
  7. 1:53 Through the ages, the river has gathered to its bed the snow-fed rivulets of the Rockies
  8. 1:58 Flowing southwestward in its wild, 1400-mile descent to the Pacific Ocean,
  9. 2:04 gouging great canyons,
  10. 2:06 piling up great deltas of silt in the valleys.
  11. 2:11 Early settlers were at the mercy of this untamed giant.
  12. 2:16 Melted snow from the mountains each spring swelled the Colorado River into a raging torrent.
  13. 2:24 flooding fertile valleys along its banks.
  14. 2:27 destroying farmlands.
  15. 2:30 poems.
  16. 2:31 and cities.
  17. 2:34 In 1905, the Colorado cut through its banks below the Mexican border
  18. 2:40 and for two years poured unchecked into the Salton sink, forming an inland sea.
  19. 2:46 After each spring's flood,
  20. 2:49 When the river had spent its fury,
  21. 2:51 It dried to a trickle.
  22. 2:53 Crops withered and died. Man and his livestock thirsted.
  23. 2:59 all living things suffered.
  24. 3:02 Settlers along the river were discouraged.
  25. 3:05 and aroused
  26. 3:06 Some gave up and went elsewhere.
  27. 3:09 Others stayed to fight.
  28. 3:12 The river had to be regulated
  29. 3:14 controlled in a year-round flow if they were to succeed.
  30. 3:18 No more floods.
  31. 3:19 No more droughts.
  32. 3:22 Arthur Powell Davis, first reclamation director and chief engineer, understood their problem. For years he had traveled up and down the river
  33. 3:32 Survey, study, build a high dam in a deep canyon upstream to control the river, he reasoned.
  34. 3:41 In 1918...
  35. 3:43 Davis reported his findings and proposals to Congress.
  36. 3:47 Congress responded in 1928.
  37. 3:49 passed the Boulder Canyon Project Act.
  38. 3:52 authorizing construction of Hoover Dam to control and regulate the Colorado River
  39. 3:57 and the All-American Canal System.
  40. 4:00 to deliver water to farmlands on the lower river.
  41. 4:03 In 1930,
  42. 4:04 President Herbert Hoover
  43. 4:06 for whom the dam is named,
  44. 4:08 signed the appropriation bill to begin construction.
  45. 4:11 Under a contract awarded in March 1931 to six companies incorporated, a combine of six major construction firms,
  46. 4:21 Men and machines went to work to build this dam of unprecedented size.
  47. 4:26 this modern,
  48. 4:27 Civil engineering wonder.
  49. 4:30 Reclamation engineers rushed to completion specifications and design drawings.
  50. 4:36 Crews at the dam site completed their surveys and investigations.
  51. 4:43 The thunder of man's determination to conquer the Colorado
  52. 4:47 reverberated between the sheer cliffs of Black Canyon as construction got underway.
  53. 4:53 The first major task was to divert the river around the dam site.
  54. 4:57 To do this, four tunnels, two on each side, were drilled through the canyon walls. Each 56 feet in diameter, they averaged 4,000 feet in length.
  55. 5:08 Drill holes were packed with dynamite and blasted.
  56. 5:12 After each explosion, shovels and trucks entered the tunnels
  57. 5:15 mucked off the shattered rock.
  58. 5:17 and dumped it in nearby gulch.
  59. 5:20 Workman excavated over one and a half million cubic yards of plaster
  60. 5:25 rock material from the four tunnels.
  61. 5:27 in 13 months.
  62. 5:30 Oh
  63. 5:32 The tunnels then were lined with
  64. 5:34 concrete three feet thick.
  65. 5:47 Explosions rocked the canyon almost daily for two years.
  66. 5:51 before actual placing of concrete in the dam began.
  67. 5:54 Oh, my God.
  68. 5:55 I'm going to go.
  69. 6:03 Acrobatic workmen called high scalers prepared the canyon walls for each blast.
  70. 6:09 Suspended on ropes, they drilled holes in the rock and loaded them with dynamite.
  71. 6:18 After each explosion, these daredevils swarmed over the cliffs.
  72. 6:22 Prying loose rock
  73. 6:24 and clearing the walls of debris.
  74. 6:32 Oh, my God.
  75. 6:35 In November 1932,
  76. 6:37 The Colorado River was diverted
  77. 6:40 under control for the first time in its history
  78. 6:44 the river flowed around and past the site.
  79. 6:48 Men and trucks dumped an earthen rock embankment across the canyon below the tunnel openings
  80. 6:54 forcing the river from its age old
  81. 6:57 through the huge diversion to
  82. 7:00 A second earth and rock dam was thrown across the river above the tunnel outlets downstream
  83. 7:06 keeping water from backing into the foundation area.
  84. 7:10 isolated and protected from the river by the two coffer dams,
  85. 7:14 The site was pumped dry.
  86. 7:16 Men and machines dug 135 feet below the old river level.
  87. 7:21 to reach bedrock for the dam's foundation.
  88. 7:24 excavating over two million cubic yards of rock
  89. 7:27 earth and sand.
  90. 7:30 As cleanup of the dam site exposed the ancient bed of the Colorado River,
  91. 7:35 Geologists read the history of what happened ages ago.
  92. 7:40 Workmen cleaned and prepared bedrock surfaces to receive the first concrete
  93. 7:45 assuring utmost stability for Hoover Dam's foundation.
  94. 7:50 12 miles upstream
  95. 7:52 drag lines, excavated sand and gravel for the dam's concrete
  96. 7:57 from an old stream bed deposit on the Arizona side
  97. 8:03 A train hauled this raw material to an aggregate plant across the river, a few miles above the dam site.
  98. 8:10 Here the sand and gravel pass through various processes of screening, grading and washing
  99. 8:16 until it emerged as unexcelled aggregate.
  100. 8:21 Then it was stockpiled according to sizes
  101. 8:24 to await its trip to the dam site.
  102. 8:28 This processed aggregate moved as called for in a steady flow over the railroad
  103. 8:33 to two mixing plants
  104. 8:35 One in the canyon bottom
  105. 8:36 and the other on the Nevada Rim.
  106. 8:39 There, sand and gravel were blended with cement
  107. 8:42 into a uniform mix.
  108. 8:44 meeting rigid specifications for the 4.5 million cubic yards of concrete to be placed in the dam structures.
  109. 9:01 From the mixing plants,
  110. 9:02 Concrete was dispatched to all points of construction.
  111. 9:06 Nine anchored aerial cableways spanning the canyon from rim to rim
  112. 9:12 lowered the concrete into the forms.
  113. 9:15 and handled other supplies and equipment as well.
  114. 9:18 As the first bucket of concrete settled into its foundation on June 6, 1933, Hoover Dam began its rise from the depths of Black Canyon.
  115. 9:29 as cableways dumped load after load of concrete into the forms. The dam soon reached its full 660 foot thickness at its base.
  116. 9:39 poured in five foot layers of concrete.
  117. 9:42 The structure's keyed or interlocking columns climb skyward as crews set new records daily.
  118. 9:50 Bucketful after bucketful ran the continuous cycle.
  119. 9:54 Mixing plant to canyon rim, out into mid-air over the gorge,
  120. 9:58 and down into the forms.
  121. 10:00 dumping its load of 16 times.
  122. 10:08 The crews vibrated and compacted the fresh pores
  123. 10:12 while buckets returned again and again to the mixing plants.
  124. 10:16 to be filled with more concrete
  125. 10:18 or other waiting forms.
  126. 10:21 Crews worked under all conditions, all seasons of the year without cessation.
  127. 10:26 Rain or shine,
  128. 10:28 day and night.
  129. 10:30 By June 1934,
  130. 10:32 One year after the first pour,
  131. 10:35 Two-thirds of the dam's concrete had been placed in the forms. Hoover Dam had risen to an impressive height
  132. 10:42 Already taking its place is one of the world's wonders.
  133. 10:46 As Hoover Dam climbed between its abutments,
  134. 10:49 Related structures also took form.
  135. 10:52 at the toe of the dam.
  136. 10:54 the U-shaped power plant to house generating equipment, control and maintenance facilities
  137. 10:59 was built in twin wings
  138. 11:01 one along each side of the canyon walls.
  139. 11:04 Intake towers, two on each side, for the power plant's penstock system, climbed as a maze of reinforcing steel and concrete.
  140. 11:14 perched on shelves hewn in the canyon walls
  141. 11:17 These graceful columns rose 403 feet
  142. 11:21 well above the dam's crest.
  143. 11:23 and the canyon rims.
  144. 11:26 Two giant spillways were set against the canyon walls on each side of the reservoir just above the dam.
  145. 11:32 These high-level controls
  146. 11:34 each capable of bypassing 200,000 cubic feet of water per second,
  147. 11:39 Assure that no water will ever overtop the dam.
  148. 11:43 Water flowing into the basins
  149. 11:46 plunges downward through the spillway tunnels.
  150. 11:49 to enter the river below the dam.
  151. 11:51 100 foot long drum gates on the spillway's crests
  152. 11:55 rise during flood stage.
  153. 11:57 to give the reservoir an additional 16 feet of storage.
  154. 12:03 Hoover Dam's Pennstock system.
  155. 12:06 called for pipes of unprecedented size.
  156. 12:09 ranging from eight and one half to thirty feet in diameter.
  157. 12:13 and five-eighths
  158. 12:15 to two and three quarters inches in thickness.
  159. 12:19 As it was not possible to ship units of this size across country, steel plate
  160. 12:25 was brought from Eastern Rolling Mills.
  161. 12:27 a steel fabrication plant
  162. 12:30 Erected especially for this job near the dam site
  163. 12:33 rolled and assembled the nearly three miles of pipe
  164. 12:36 installed in the canyon wall tunnels.
  165. 12:39 As in all unprecedented phases of Hoover Dam's construction,
  166. 12:43 Fabrication of the pipe sections required special machinery and equipment.
  167. 12:48 Edges of the dimension plates were shaped on a planing machine to assure precision and accuracy of later steps in their manufacture.
  168. 12:56 Then...
  169. 12:57 They were bent on a giant press
  170. 12:59 and rolled into circular form.
  171. 13:02 one such plate
  172. 13:03 equaled one third the complete circumference of a finished pipe. Three of the largest curved plates welded together
  173. 13:11 formed a ring 30 feet in diameter
  174. 13:13 and 11 feet long.
  175. 13:16 two of these rings joined
  176. 13:18 Meet up a section.
  177. 13:19 weighing 150 to 184 tons.
  178. 13:24 A vertical lathe.
  179. 13:26 machined the edges
  180. 13:27 so the sections would fit precisely when joined into continuous penstocks inside the canyon walls.
  181. 13:35 A train passing through one of the 30-foot sections
  182. 13:39 reveals their comparative size.
  183. 13:42 When the intake towers and their connected tunnels were ready to receive the pen stops,
  184. 13:47 a specially designed trailer, all the sections one at a time
  185. 13:51 down the highway from the plant to the dam site.
  186. 13:55 At the canyon rim.
  187. 13:56 A 150-ton cableway relieved the trailer of its tremendous burdens
  188. 14:02 swung the pipe sections out over the gorge.
  189. 14:05 and lowered them under absolute control.
  190. 14:15 Trailers waiting at portals of the access tunnels
  191. 14:18 carried them to their permanent connections inside the main tunnels.
  192. 14:23 The five sections were hoisted into location with cables
  193. 14:27 and joined end-to-end pressure pins to form continuous conduits between the intake towers, turbines and outlet valves.
  194. 14:37 While this and other work on the pertinent features was going on,
  195. 14:41 a continuous stream of concrete had been pouring into the dam for him.
  196. 14:46 The structure neared its full height of 726 feet.
  197. 14:50 far above the crest of any other dam yet built by man.
  198. 14:58 On May 29th, 1935,
  199. 15:01 Two years after they had begun pouring,
  200. 15:03 Cruz placed the last concrete in Hoover Dam.
  201. 15:07 a total of three and one quarter million cubic yards.
  202. 15:12 this modern civil engineering wonder stood completed
  203. 15:16 two and one half years
  204. 15:18 ahead of schedule.
  205. 15:21 On September 30, 1935,
  206. 15:24 President Franklin Delano Roosevelt dedicated to Hoover Dam.
  207. 15:28 to the nation's progress.
  208. 15:30 He praised its designers and builders.
  209. 15:33 The dam stood like a sentinel
  210. 15:36 white and beautiful in the desert sunlight.
  211. 15:39 guarding the river and its downstream wealth.
  212. 15:42 Flood waters lapped helplessly against its arched back
  213. 15:45 as the reservoir fills.
  214. 15:47 This man-made inland sea spread into the valleys and canyons among the colorful hills and mountains.
  215. 15:55 Hoover Dam
  216. 15:56 had conquered the Colorado.
  217. 16:02 Turbine pits to hold Hoover Dam's 17 big hydroelectric units were built into the powerhouse.
  218. 16:09 Generator installations began in 1935.
  219. 16:12 The first generator, Unit M2, began commercial operation October 26th
  220. 16:20 to serve the city of Los Angeles.
  221. 16:23 ones and twos,
  222. 16:25 The generators filled the pits.
  223. 16:27 as demand for electrical energy in California, Nevada and Arizona
  224. 16:31 called them into service.
  225. 16:33 Finally in 1959
  226. 16:36 Manufacture and installation of the last generator, N8.
  227. 16:40 THE GAP.
  228. 16:42 For 25 years, the N8 pit had lain dormant in silence.
  229. 16:47 except for the hum of other Hoover generators.
  230. 16:50 now
  231. 16:51 As more generating capacity was needed,
  232. 16:54 contracts were awarded for the generators manufacture and installation.
  233. 16:58 Plants throughout the nation
  234. 17:01 fabricated N8's many parts.
  235. 17:04 The design of N8 followed that of other Hoover-generating units.
  236. 17:09 It is a 95,000 kilowatt
  237. 17:12 60 cycle
  238. 17:13 16,500 volt generator driven by a 115,000 horsepower turbine.
  239. 17:21 Falling water from the reservoir which spins and powers the turbine wheel
  240. 17:26 is controlled by a huge butterfly valve.
  241. 17:29 which permits the water to flow to the turbine from the feeder penstock.
  242. 17:33 Weighing 2,000 tons, N8 parts were shipped to Hoover Dam
  243. 17:38 on 60 rail cars.
  244. 17:41 Arriving at the canyon rim overlooking the dam, the parts were lifted by cableway and
  245. 17:50 out over the canyon,
  246. 17:51 and down to the powerhouse.
  247. 17:55 Parts descending into the gorge on strands of cable were familiar and almost daily sights, reminiscent of previous installations.
  248. 18:04 and the main cableway operator was the same one who had helped install and operate the cableway
  249. 18:10 during the dam's construction in the early 1930s.
  250. 18:14 Others likewise had worked on the project
  251. 18:17 throughout its construction.
  252. 18:28 Inside the Nevada wing of the powerhouse,
  253. 18:31 technicians assembled and installed the mass of electrical cargo.
  254. 18:36 crews prepared the N8 pit
  255. 18:39 to receive the new generating unit.
  256. 18:41 They removed temporary slabs over the turbine and relief valve outlets to the tailrace river.
  257. 18:48 Liners assembled in these openings were set in concrete.
  258. 18:52 The turbine's scroll case sections were lowered into the pit.
  259. 18:56 sections were leveled
  260. 18:58 bolted together
  261. 18:59 and a lie.
  262. 19:01 The completed scroll case was then anchored in concrete.
  263. 19:06 Later, the turbine's water wheel
  264. 19:08 attached to the bottom end of the shaft
  265. 19:11 was installed inside the case.
  266. 19:15 The butterfly valve was assembled on the generator floor
  267. 19:18 and later connected between the feeder pen stock
  268. 19:21 and the turbine scroll case.
  269. 19:23 Meanwhile, the generator's two main parts, the rotor and stator, took form.
  270. 19:29 Steel lamination plates were stacked around the rotor and stator frames.
  271. 19:34 Coils were locked into place.
  272. 19:36 and electrical connections were made.
  273. 19:41 The powerhouse's overhead cranes lifted the completed 254-ton stator
  274. 19:46 from its erection bay
  275. 19:48 and carried it gently to its foundation over the turbine pit.
  276. 19:51 where it was lowered and bolted into place.
  277. 19:56 Amen.
  278. 19:56 466 ton rotor
  279. 19:59 was moved from its erection bay
  280. 20:01 and lowered inside the stator.
  281. 20:04 The rotor was then joined to the turbine water wheel by a 38-inch diameter shaft.
  282. 20:09 63 feet long.
  283. 20:11 Guide and thrust bearings and other parts were added
  284. 20:14 to complete the assembly.
  285. 20:17 After test runs.
  286. 20:19 N8 went on the line December 1st, 1961.
  287. 20:23 to serve the state of Nevada.
  288. 20:25 and to complete the Hoover power plant.
  289. 20:28 raising its capacity to one and one third million kilowatts.
  290. 20:33 keeping it as one of the world's largest hydroelectric installations.
  291. 20:38 As the last sounds of construction faded into history,
  292. 20:42 Hoover Dam had cost $175 million.
  293. 20:47 less a deferred payment of $25 million allocated to flood control,
  294. 20:52 Hoover Dam's cost
  295. 20:53 is being returned to the federal treasury
  296. 20:56 At 3% interest,
  297. 20:57 from the sale of hydroelectric power.
  298. 21:02 Hoover Dam has fulfilled the hopes and expectations
  299. 21:05 of those who envisioned this great reclamation project.
  300. 21:10 Colorado River waters
  301. 21:11 that once destroyed man and his property
  302. 21:15 Now serve him.
  303. 21:19 The Colorado pours its waters into Lake Mead, named for Dr. Elwood Mead, Reclamation Commissioner during construction.
  304. 21:29 Lying calmly behind the dam, these waters await need by downstream users.
  305. 21:35 Water is released through the Hoover Power Plant turbines in a year-round flow
  306. 21:40 to irrigate over one and one quarter million acres of desert land.
  307. 21:44 serve municipal and industrial needs of the Pacific Southwest, generate hydroelectric energy,
  308. 21:51 and provide various other multipurpose benefits.
  309. 21:55 The clear waters of Lake Mead have opened up a vast new recreational
  310. 22:00 fish and wildlife vacation land for America.
  311. 22:03 Millions beat paths to this one-time wilderness along the Colorado River to the picnic
  312. 22:09 Go boating.
  313. 22:11 swim,
  314. 22:14 Fish.
  315. 22:15 and enjoy these important outdoor reclamation products.
  316. 22:27 Hoover Dam and its power plant work around the clock
  317. 22:30 to serve water and power needs of the Pacific Southwest
  318. 22:34 Water from Lake Mead?
  319. 22:36 passing into the intake towers,
  320. 22:38 falls over 500 feet through the penstocks
  321. 22:41 to spin the giant turbine wheels
  322. 22:44 and then discharged to the river.
  323. 22:46 This action is repeated at downstream reclamation dams.
  324. 22:51 Amen.
  325. 22:51 Transformers step up Hoover Dam voltage,
  326. 22:54 as it comes from the generator.
  327. 22:57 Lines carry this power up over the powerhouse roof.
  328. 23:00 to the switch yards.
  329. 23:02 From there,
  330. 23:03 It is transmitted over lines across the desert.
  331. 23:09 The river flows southward.
  332. 23:11 and along the way man diverts from the controlled stream
  333. 23:15 to sustain his prosperous way of life.
  334. 23:19 67 miles downstream, Davis Dam re-regulates the Colorado's flow
  335. 23:25 releasing water through its power plant turbines to irrigators in this country in Mexico.
  336. 23:32 Davis Dam generators interconnect with those at Hoover Dam upstream
  337. 23:36 and those at Parker Dam downstream.
  338. 23:39 This energy goes out over transmission lines of the Parker Davis project
  339. 23:44 with farms, homes, and factories.
  340. 23:47 Much of this Colorado River energy pumps the farmers' irrigation and drainage water.
  341. 23:54 Parker Dam,
  342. 23:55 155 miles downstream from Hoover Dam,
  343. 23:59 was built with funds advanced by the Metropolitan Water District of Southern California
  344. 24:05 Parker Dam provides a forebay for the District's Colorado River Aqueduct.
  345. 24:09 Another one of America's seven
  346. 24:12 modern civil engineering wonders.
  347. 24:15 Electrical energy from Parker and Hoover power plants.
  348. 24:18 pumps water along the aqueduct.
  349. 24:21 This waterway delivers municipal and industrial supplies to the Los Angeles and San Diego coastal areas.
  350. 24:28 Parker Dam also controls floods.
  351. 24:32 Below Parker Dam, Headgate Rock Dam.
  352. 24:36 diverts water to Colorado River Indian Reservation lands in Arizona.
  353. 24:41 and farther downstream
  354. 24:43 The Palo Verde Diversion Dam sends water to the Palo Verde Irrigation District.
  355. 24:48 oldest irrigation development on the Colorado River.
  356. 24:52 At Imperial Dam and De-Silting Works
  357. 24:55 300 miles downstream from Hoover Dam,
  358. 24:59 Colorado River water enters river-sized canals
  359. 25:02 to irrigate farmlands in California and Arizona.
  360. 25:08 The All-American Canal system carries part of the Colorado's flow
  361. 25:12 westward to the Yuma, Imperial, and Coachella valleys.
  362. 25:17 When water reaches its farthest point on this canal system,
  363. 25:21 It has traveled nearly 500 miles after leaving Hoover Dam
  364. 25:26 and has required 10 days to make the trip.
  365. 25:32 The Gila Gravity Main Canal takes water from Imperial Dam
  366. 25:36 South and East
  367. 25:38 to valley and mesa lands of the Gila and Yuma Auxiliary Projects.
  368. 25:43 Mexico's share of Colorado River water to irrigate lands below the border
  369. 25:48 passes Imperial Dam and most of it is diverted at Morelos Dam
  370. 25:53 into the Alamo Canal.
  371. 25:57 the non-surplus food, fiber, and forage crops
  372. 26:00 grown on lands nourished by water from Hoover Dam.
  373. 26:04 Find ready markets throughout the nation.
  374. 26:08 while snow-covered lands lie idle,
  375. 26:10 Winter fruits and vegetables grown in the warm southwest with Colorado River water are shipped to dinner tables across the nation.
  376. 26:21 In return, these irrigated areas buy farm machinery and other products from the manufacturing center.
  377. 26:31 This exchange of goods between west and east, north and south,
  378. 26:35 has helped develop America's free enterprise prosperity.
  379. 26:45 Hoover Dam has pointed the way to the fullest utilization of the Colorado River's resources.
  380. 26:51 Man is adding other mighty reclamation projects to the stairway of dams on the Colorado River.
  381. 26:57 In northern Arizona, Glen Canyon Dam has joined Hoover Dam in conquering and regulating the Colorado.
  382. 27:05 potential sites and other canyons on the Colorado River
  383. 27:08 Await the day when they too
  384. 27:10 will cradle mighty multi-purpose dams.
  385. 27:14 These developments will write new chapters
  386. 27:17 in the story of Hoover Dam.
  387. 27:19 Truly.
  388. 27:20 a modern
  389. 27:21 Civil engineering wonder.